Decommission details
- Hostname and asset tag
- Purpose it served
- Owner team
The risk in decommissioning is rarely the shutdown; it is the dependency nobody knew about and the data nobody checked for. This checklist front-loads both, and ends with the licence and backup cleanup that pays for the exercise.
Discover dependencies before announcing a date. Check connection logs, DNS queries, firewall hits, and scheduled jobs pointing at the host. Asking teams whether they use a server reliably under-reports, because people do not know what their applications connect to.
Power off and wait before wiping. Leave the host powered off but intact for two to four weeks. Anything you missed surfaces as a complaint you can reverse in minutes rather than restore from backup.
Capture erasure evidence. Record the erasure method and a certificate or log reference. Auditors ask about data destruction, and reconstructing it afterwards is impossible once the hardware has gone.
Here's a preview. Unlock the free download to get all 4 sections (3 more below).
More free templates IT teams use alongside this one.
Servers built ad hoc are the ones missing from monitoring and backup, discovered during an incident or an audit. This checklist exists so that every build ends in the same known state regardless of who did it.
The risk in asset disposal is not the hardware value, it is the data. A device leaving the building with recoverable data is a breach you have voluntarily handed to a third party, and the only defence is per-device erasure evidence.
Most asset registers die of one disease: nothing in the organisation forces them to be updated. This one is built around the three events that actually change an asset's state (assignment, repair, and disposal), so the register is maintained by the work rather than by an annual audit.
Discover dependencies, confirm data retention and take a final backup, power off and leave intact for a soak period of two to four weeks, then securely erase, dispose, and reclaim licences, backup jobs, monitoring, and IP addresses.
Two to four weeks is common, and the window should cover at least one full business cycle including month-end. A dependency discovered during the soak is reversible in minutes; one discovered after erasure is a restore.
The erasure method used, the standard it meets, the date, who performed it, and a certificate or log referencing the specific device serial. Capture it at the time. It cannot be reconstructed once the hardware has left.